Masterplan and new clean room production building
BRAND GmbH & Co. KG, Wertheim, Germany
For BRAND, Dr. Schönheit + Partner prepared a master plan for the existing plant in Wertheim (40,000 m²) and for the development of a new site (39,000 m²) in order to plan possible expansion steps at an early stage. The first major construction project of this long-term plant development strategy was the expansion of the existing injection molding production, which was carried out in clean room quality.
Based on the continuation of the company's strategy and the long-term development of the production program, the first step was to determine the growth and change requirements of the existing buildings and open spaces. The master plan is characterized by the systematic flow of materials and people through the entire facility (planning from the inside out).
The first major construction project in the master plan was the expansion of the existing BRAND injection molding facility (BSZ) by approximately 4,200 m². The highlight of this injection molding center is the new, cost-consciously and aesthetically planned clean room of approx. 3,200 m². It provides optimal production conditions with a high degree of cleanliness and safety.
The air in the cleanroom is extracted through double-shell walls and re-introduced through airbags in the suspended ceiling. White is the dominant color throughout the cleanroom. The building's technology is easily accessible on the roof. The logistics zone provides a connection to the logistics center for route traffic. A high degree of adaptability and a consistent color concept provide the best conditions for flexible production in the future.
The new injection molding production hall, which houses the clean room area, combines flexibility and adaptability with a unique corporate architecture. The building can grow inward and outward to meet the needs of the coming years. At the same time, the building lays the foundation for a consistent corporate architecture concept for BRAND.
BRAND has been a trusted partner and reference in the laboratory sector for more than 70 years. We are one of the world's leading manufacturers of liquid handling and life science products. Approximately 500 employees develop and produce BRAND products at the Wertheim site. The claim "simple, easy and efficient" stands for the claim to make laboratory work easy, uncomplicated and efficient with innovative products and perfect quality.
KPIs at a glance
m €
investment
m²
production area
months
construction time
All relevant services under the same roof:
- Factory planning
Development of production program, definition of logistics processes, dimensioning of storage areas - Architecture
Planning through to implementation (service phase 1 to 9) - Project management
Deadline, quality and cost monitoring, as well as moderation of project and planning discussions (service phase 1 to 5 in accordance with AHO)